Have a look and see the progress that’s being made on our building project, most recent at the top.

For the full journey, start at the bottom of the page.

To learn more about our building project, click here to go to the main page.

Check back for the most recent pictures!!

 

March 2017 – The keys in our hands

IMG_0503 RZ

P1200128 RZ

 

P1200127 RZ

P1200140 RZ

P1200134

P1200146 RZ

P1200144 RZ

P1200189 RZ

P1200188 RZ

P1200197 RZ

P1200204 RZ

P1200196 RZ

 

 

January 2017 – Exterior

 

img_0335

img_0334

 


December 2016 – Dividers installed

The moving dividers to help change the space as required are hung from beams above.

img_1664

 

The Kitchen is installed upstairs.

img_1661

 

 

December 2016 – The ceilings

Ceilings, light fittings and walls are added, finished and painted as the near final electrical work is done.

img_1641-2016-12-02t23_11_37-252

img_1642-2016-12-02t23_10_39-655

img_1647

 


November 2016 – The inside

With the outer workings complete, the glass fully on and the scaffolding gone, the work is concentrated to the inside.

The internal glazing goes in, the doors and other woodwork are added. The heating and lighting is switched on.

img_1633

img_1645

img_1646-2016-12-02t23_09_18-625

 


July 2016 – The Video

 

Imagining life in the new Church Centre from St John’s Egham on Vimeo.


May 2016, The External Stone

External stonework to bring the building visually closer to the church is wrapped around the building.

IMG_9243

 

The stone to be laid is unstacked from delivery pallets.

IMG_9280

 

Located just to the left of the glass atrium, the engraved stonework is now visible, showing the building’s ownership, completion year, and a message from the Bible.

IMG_9245

 


 

May 2016, The Offices

The complementary, not to be confused with complimentary, arched windows are installed in the offices, these are adjoining the church building.

IMG_9262

 

Work for the church and you too will be able to look out of windows like these in real life.

IMG_9253

 


 

May 2016, The Walkthrough

From the Church’s ground floor, the wall has been opened up in what was previously the vicar’s vestry to provide some access to the new building.

IMG_9263

 

Ducting continues to go in, taken from inside the kitchen.

IMG_9275

 

A man in a gas mask spray paints the exposed steelwork, changing it in the picture from extremely boring grey to a much cleaner white.

Notice the floor in here is a different colour, this is because the heating in the floor has now been installed, and been screeded.

IMG_9274

 


 

April 2016, Above and below the ceiling

On the ground floor, the ducting and pipes go in.

IMG_8476

IMG_8483

IMG_8486

 

The roof is well underway on the first floor. This view is from the far corner where the kitchen is to be situated.

IMG_8487

 

These spaces under the wooden area will be glass, just in case we didn’t explain it well before.

IMG_8490

 

Here is the entrance to the new kitchen on the first floor complete with tastefully angled serving hatch. We are assured the red circles are not the decorators deciding on what paint to use.

IMG_8491

 


 

March 2016, On the roof

The view of the roof looking from the church, the raised section of roof will be glass sided.

IMG_8149

 

The overall building height is shown, the glass link will be in this area.

IMG_8138

 


 

Mid March, Exterior touches

Here, you can see the matching bricks meet with the rest of the church building, where new staff offices will be, below the vicar’s vestry.

P1150894

 

Here are those windows completed, except the glass.

P1150977


 

Early March, The walls reach the roof

One of the next milestones is to weatherproof the building, to do that, the walls must reach where the roof will be.

Views from the stairs of the first floor.

IMG_8122

 

The extra steelwork on the roof here will be glass sided to let light in, though not as much light as shown here!

IMG_8113

 

Here, the scaffolding surrounds the building as the block-work continues to rise.

P1150906

 

The building as seen from the West. (On the path from the Church to the Caddey.)

IMG_8108

 

People stand inside the first floor.

IMG_8125


 

February, The Ground Floor

The view from inside the glass atrium, with the stairs to the top floor on the left, and the entrance to the lift.

IMG_8177

 

The large windows can be seen, they will eventually look out to the grounds.

IMG_8180

 


 

January/February, The Blockwork Begins. With the steel frame complete, the blocks can be laid forming the walls and the floors.

The concrete lift shaft can be seen, the ground floor walls are also present. The ladder leaning there is for the construction workers, there will be stairs in another location, we promise.

IMG_8093

 

Interior block-work can be seen on the first floor, this will be the main kitchen.

IMG_8112

 


 

January 2016 Part of the timelapse video, the steelwork went up over the course of the month.

Screen Shot 2016-01-19 at 15.53.08 Screen Shot 2016-01-25 at 11.36.13  Screen Shot 2016-02-06 at 10.27.12 Screen Shot 2016-02-25 at 10.56.45

 


 

Sunday 3rd January 2016, Praying on the footprint of the building.

P1150789 P1150801